Thursday, December 19, 2024
Advertisement
  1. You Are At:
  2. News
  3. India
  4. Mumbai-Ahmedabad bullet train project: Bombay HC permits felling of 20,000 mangrove trees

Mumbai-Ahmedabad bullet train project: Bombay HC permits felling of 20,000 mangrove trees

Mumbai-Ahmedabad bullet train project: The Bombay High Court allows to cut around 20,000 mangrove trees for a Mumbai-Ahmedabad bullet train project.

Reported By : PTI Edited By : Bhagya Luxmi
Mumbai
Published : Dec 09, 2022 12:56 IST, Updated : Dec 09, 2022 12:56 IST
bombay high court, bombay high court news, bombay high court latest news, mumbai, ahmedabad, mumbai
Image Source : PTI (FILE) 20,000 mangrove trees to fell for Mumbai-Ahmedabad bullet train project, Bombay HC permits NHSRCL

Mumbai-Ahmedabad bullet train project: The Bombay High Court allows the chopping of around 20,000 mangrove trees for a bullet train project. A division bench on Friday allows the National High Speed Rail Corporation (NHSRCL) to cut down trees for the Mumbai-Ahmedabad bullet train project. The NHSRCL in 2020 filed a petition seeking permission to fell mangrove trees in the city and neighbouring districts of Palghar and Thane. 

A division bench of Chief Justice Dipankar Datta and Justice Abhay Ahuja allowed the NHSRCL to cut the mangrove trees for the above-mentioned public project. As per a 2018 order of the high court, there exists a "total freeze" on the destruction of mangroves across the state and permission has to be sought from the high court each time an authority wishes to fell mangroves for any public project.

As per the said order, a 50 m buffer zone must be created around the area that hosts the mangroves and no construction activity or dumping of debris can be permitted within this buffer zone. In its petition filed in 2020, the NHSRCL had assured the court it would plant five times the total mangrove trees that were earlier proposed to be felled and the number would not be reduced for the same.

The plea was opposed by 'Bombay Environmental Action Group', an NGO, on the ground that no study was undertaken about the survival rate of saplings to be planted as a compensatory measure and the Environmental Impact Assessment report for felling trees has not been provided. The NHSRCL had denied the objections raised by the NGO and claimed that it had availed required approvals for the felling of trees for the project of public importance and would compensate the loss occurring due to the same by planting of saplings as directed.

The 508-km high-speed rail corridor between Ahmedabad and Mumbai is expected to cut travel time from six-and-a-half hours to two-and-a-half hours. The bullet train project received a major push after the Eknath Shinde-Bharatiya Janata Party (BJP) government came to power in June this year. The dispensation has given all approvals for this project, the foundation of which was laid by Prime Minister Narendra Modi in September 2017.

Also Read: Mumbai-Ahmedabad bullet train: NHSRCL seeks bids for construction of India's first undersea tunnel

Also Read: Mumbai-Ahmedabad Bullet Train: Railways sacks NHSRCL MD, in-charge of high-speed rail project

Advertisement

Read all the Breaking News Live on indiatvnews.com and Get Latest English News & Updates from India

Advertisement
Advertisement
Advertisement
Advertisement