Friday, December 27, 2024
Advertisement
  1. You Are At:
  2. News
  3. India
  4. Agra Metro Rail project picks momentum despite Covid alarm

Agra Metro Rail project picks momentum despite Covid alarm

Construction work on the Agra Metro Rail project continues at a brisk pace, amid a surge in covid 19 cases

Edited by: IANS Agra Published : May 11, 2021 7:58 IST, Updated : May 11, 2021 7:58 IST
Metro
Image Source : PTI

Construction work on the Agra Metro Rail project continues at a brisk pace, amid a surge in covid 19 cases

While the city and its vast rural hinterland continue to reel under Covid-19 with an alarming rise in the number of fresh cases in the past 20 days, construction work on the Agra Metro Rail project continues at a brisk pace.

The momentum has been maintained largely due to extensive arrangements made for prompt medical care to the large workforce at the sites.

Groups of 15 have been formed to work in a coordinated manner, avoiding proximity.

Officials at the sites said provision had been made for gloves, masks, and shields. Thermal screening and continuous monitoring of health parameters have been ensured and all workers made aware of the gravity of the pandemic. A doctor and a nurse have been stationed at the casting site just in case any laborer needs medical attention. In a record, five-month period 400 piles have been completed.

"It has been five months since December 7, 2020 when Agra Metro construction work was inaugurated by Prime Minister Narendra Modi. During this entire period Agra Metro has achieved fast progress and several milestones in the civil construction work of Agra Metro," an official said.

Of the total 686 piles, 400 for the 3 km elevated section of priority corridor from Taj East Gate to Jama Masjid have been completed to date. Along with this, 45 pile caps and 16 piers have also been completed for this section from Taj east gate to Fatehabad road.

The Managing Director, UPMRC Kumar Keshav said, "Vigour and Enthusiasm of UPMRC team are unbeatable. Agra Metro has achieved completion of 400 piles today in spite of all odds. Congratulations to the team of Engineers of UPMRC, who have made this possible with their efforts."

It is to be noted that Agra Metro Project's civil construction work is going on for the Priority section of the first corridor, which runs from Taj East Gate to Sikandara. The priority section is a 6 km stretch from Taj East Gate to Jama Masjid, which comprises of 3 km elevated and 3 km underground section.

Also Read: Delhi Metro services to remain suspended from Monday till May 17 morning: DMRC

Advertisement

Read all the Breaking News Live on indiatvnews.com and Get Latest English News & Updates from India

Advertisement
Advertisement
Advertisement
Advertisement