Sunday, December 22, 2024
Advertisement
  1. You Are At:
  2. News
  3. Mizoram
  4. Mizoram govt incurred Rs 4.88 crore wasteful expenditure due to negligence: CAG

Mizoram govt incurred Rs 4.88 crore wasteful expenditure due to negligence: CAG

Chief Minister Zoramthanga tabled the CAG report in the recently concluded Assembly, in which it said that the construction of the Darlak-Sihthiang road was undertaken under the Pradhan Mantri Gram Sadak Yojana (PMGSY) despite the village being already connected.

Edited By: India TV News Desk Aizawl Published : Aug 28, 2023 12:27 IST, Updated : Aug 31, 2023 10:11 IST
Mizoram CM Zoramthanga
Image Source : PTI Mizoram CM Zoramthanga

The Comptroller and Auditor General (CAG) of India has hit out at the Mizoram government for incurring an "avoidable" expenditure of nearly Rs 5 crore on formation cutting of Darlak-Sihthiang road in Mamit district due to "negligence".

Chief Minister Zoramthanga tabled the CAG report in the recently concluded Assembly, in which it said that the construction of the Darlak-Sihthiang road was undertaken under the Pradhan Mantri Gram Sadak Yojana (PMGSY) despite the village being already connected.

It said that Sihthiang was connected by 11-km long Chuhvel-Sihthiang paved road, which is an all-weather road since December 2020.

While the construction of the Chuhvel-Sihthiang paved road was being taken up in May 2016, an agreement was signed in August 2019 between Mizoram Rural Road Development Agency of the state Public Works department and contractors for the construction of Darlak-Sihthiang road at a cost of Rs 52.81 crore and the project was scheduled to be completed by June 2020.

"The Detailed Project Report (DPR) for construction of Darlak-Sihthiang road indicated that Sihthiang village, with a population of 495 was unconnected from any part of Mamit district and the length of the proposed Darlak-Sihthiang road was 35.61 km and the estimated project cost was Rs 58.32 crore," the audit report said.

The contractor started the work in February 2020 and completed the formation cutting of 7.3 km in June 2021.

However, the work was put on hold since July 2021 due to non-availability of Forest clearance and the department proposed for dropping of the project to the Ministry in July 2022, it said.

Out of the contract value of Rs 52.81 crore, the PWD incurred expenditure of Rs 4.88 crore till April 2022.

The CAG report pointed out that the expenditure of Rs. 4.88 crore on formation cutting of this road was "wasteful as the project was proposed to be dropped".

(With PTI inputs)

Advertisement

Read all the Breaking News Live on indiatvnews.com and Get Latest English News & Updates from Mizoram

Advertisement
Advertisement
Advertisement
Advertisement