However, since then the Kolkata-class has suffered consecutive delays, slow construction procedures and technical problems which will now see the first of the class now enter service during early 2014.
The delays in the construction programme have been attributed to - persistent design changes made by the Indian Navy to incorporate new weapons systems and sensors, failure by a Ukrainian shipyard to deliver the ship's propellers and shafts and the contract later being awarded to a Russian firm.