ASI stops restoration work of Kedarnath temple due to winter

New Delhi : The Archaeological Survey of India (ASI) has stopped restoration work of Kedarnath Temple, which was ravaged by the flash flood in June, after the doors of the sanctum sanctorum was closed due


The ASI, in first phase, has removed parts of debris deposited on the southern, western and eastern side.  Nearly 489 cubic meter of debris deposit has been removed from the plinth and approximately 635 square metre area of plinth has been cleared.


The ASI team executed the work at site, despite difficult working conditions compounded due to harsh weather conditions and snowfall.

Also, the necessary stone packing to the damaged portions of the temple walls had been done. Replacement of damaged wooden door on the western side of the temple has been also completed.

Apart from it, cleaning of Garbha Griha walls has been done up to about nine feet height.

The ASI team is preparing a total station survey plan of about 50 X 50 meters of the temple site for which field data has been collected with the Geological Survey of India (GSI).